Schedule (Overall & Two-Week Look Ahead)

Downtown Area Wastewater Treatment Facility & Effluent Disposal Contract 2019-01

  • The Contractor updates the project schedule monthly and will be uploaded when received.
  • The project schedule is based on the actual construction activities and trades working at both the wastewater treatment facility site and the effluent disposal site. Crews will be added when production warrants. 
  • The schedule will be broken down by category at each of the sites including, but not limited to, site work, concrete work, equipment installation, accessory equipment installation, and start-up and training.

Downtown Area Collection System & Pumping Station Contract 2019-02

  • The Contractor updates the project schedule monthly and will be uploaded when received.
  • The project schedule is based on the minimum number of crews as specified in the contract (mainline crew, service crew, restoration and paving crew).  Crews will be added when production warrants. 
  • The schedule will be broken down by pump station tributary area including, but not limited to, roadways, pumping stations, Route 6 crossing and temporary and permanent pavement restoration.