Notice for Meetinghouse Pond Sewer Abutters: 

 Construction work is ongoing on School Road from Town Hall toward Monument Road. Town Hall parking is restricted to the parking lot at 139 Main Street (across the street from Town Hall). Police Details are on-site to help with access to Town Hall. The Town Hall parking lot will open when the work and equipment have moved far enough down School Road to safely allow access to the parking lot entrance.

Gravity sewer construction will continue to Monument Road toward Pond Road the week of October 23rd (tentative). 

Low-pressure sewer construction will begin on Lake Farm Lane within the next two weeks.

 The Contractor will be updating the construction schedule. For more information on the locations and construction details, please visit the following link:

 Construction Activities & Detours - Three-Week Lookahead


Notice for Downtown Area Sewer Abutters: 

Please click here to view the table of Estimated Betterment Values.


Please visit the Sewer Service Connections webpage for resources and information for property owners located within the Downtown Area. See below for the Connection Schedule.

2023-01-05-Orleans_MA_Downtown_Area_Connection_Schedule